Thursday, January 15, 2015

Dispute Boards as economically efficient resolution of disputes


          It is commonly perceived that Dispute Boards serve as the impetus for reducing a contractor’s bid pricing.

                  Dispute Boards provide economically efficient resolution of disputes on construction and infrastructure projects without any delay or with much less costs than disputes

                  Many contracts will specify that the Dispute Board must give its decision or recommendation within a specified timescale (84 days in the latest FIDIC Red Book), which will be far faster than one could expect to obtain a decision from arbitration or litigation

                  In a Standing Dispute Board, the amount to be paid to the Board (usually the 0.01 - 0.02% of the project value[1]) is for all of the fees for the life of the project no matter how many disputes come before the Board

                  An ad hoc Dispute Board is clearly a cost saving with only appointing a Dispute Board when it is required to resolve a particular dispute. However, an ad-hoc board will not have the background knowledge of the project that a standing board would have, and therefore will likely take longer to consider a dispute than a standing board would

                  Whilst the Dispute Board may request further materials,  there are typically no requirements for disclosure of documentary evidence beyond the need, which also saves significant costs

          To summarise the affect of the DB boards on overall costs of the project, one must consider pros and cons in light of what has already been discussed:

          Indeed, The  DB provides the parties with a dispute resolution process that is relatively speedy and less costly than court or arbitration proceedings,  

          BUT such proceedings may be avoided only temporarily if a party is dissatisfied with the decision of the adjudication panel

          Panels are commonly required to provide decisions within a relatively short period of time (typically within three months of a referral), which reduces overall costs

          BUT  this means the panel may sometimes not be able to conduct an in-depth and rigorous analysis of all the relevant (factual and legal) issues

          The Board members have necessary skills and technical expertise in the subject matter,

          BUT sometimes such DB decisions may be more ‘technical’ than ‘judicial’ in nature. That may not be appropriate for the final determination of the dispute
 
          The construction disputes might involve multiple parties. In the UK the situation is more complex because of the parties' statutory right to adjudicate

          However, unless parties specifically agree, the panel usually does not have the power  to require disputes arising under different contracts to be joined or consolidated with disputes arising under the same contract in question and same parties involved.

 
  The  DB is less formal procedure  and the Board members the wide freedom generally given to the panel to act as experts and investigate the facts

  However, panel's proceedings may prove difficult to control. Analysis of English case law[1] suggests that enforcement of a Dispute Board's decision may be refused if there has been a lack of fairness in the procedures adopted
 

Conclusion

To sum up, the Dispute Boards review or adjudication is an appropriate method as a conflict control and prevention mechanism in the contract to promote collaboration between business partners so they can solve problems early and avoid more costly end-point conflict resolution processes

 

[1] RSL (South West) Ltd v. Stansell Ltd [2003] EWHC 1390 (assistance was sought from a programming specialist, but the parties are not given an opportunity to comment on the final report prepared by him) ; Discain Project Services Ltd v. Opecprime Development Ltd. [2001] BLR 285 (one party was consulted upon submissions made by the other without a reciprocal process);  Woods Hardwick Ltd v. Chiltern Air Conditioning [2001] BLR 23 (the failure to make available to one party information obtained from the other party and various third parties); Balfour Beatty Construction Limited v. Lambeth London Borough Council (use of an analysis different to that advanced by the parties without informing the parties of the proposed methodology and without seeking their observations on its suitability) See overview of the cases in Dispute Boards, Chapter 5  in Jane Jenkins , International Construction Arbitration Law, Arbitration in Context Series, Volume 3.  p. 116,  at

 



[1] C. Chern, The Role of Dispute Boards in Construction – Benefits without Burden.

No comments:

Post a Comment